Sizing a Transformer for Motor Loads: Starting kVA, Voltage Dip and the Right Starting Method
Running kVA is only half the story. A motor started direct on line pulls about six times its rated current, and that surge is what decides whether the transformer holds up at every start.
When sizing a transformer for motor loads, running kVA is only the first check. The second is starting: a motor started directly on line draws about six times its rated current, and that surge pulls down the secondary voltage. The dip is roughly the starting kVA divided by the short-circuit capacity at the bus, so a bigger or lower-impedance transformer, a softer starting method or a VFD all reduce it. Check both before you buy.
Why Running kVA Is Not Enough
A transformer sized only for running load can look perfect on paper and still fail the plant at startup:
- Lights flicker and contactors drop out.
- The motor fails to accelerate, because torque falls with the square of voltage.
- Sensitive equipment on the same bus trips.
Our transformer capacity example for a 1600 kVA unit covers running-load sizing. This guide adds the starting check.
Step 1Calculate the Motor's Starting kVA
When you size a transformer kVA for motors, two figures matter: the running kVA and the starting kVA. The running kVA comes from the motor rating; the starting kVA is the surge the transformer has to supply for a few seconds at every start.
Rated kVA = kW ÷ (power factor × efficiency)
Starting kVA = rated kVA × starting multiple
Typical starting multiples (check the motor data sheet):
| Starting method | Starting current (× rated) | Note |
|---|---|---|
| Direct on line (DOL) | about 6 | Highest dip and highest torque |
| Star-delta | about 2 | Starting torque falls to about one third |
| Soft starter | about 2 to 4 | Adjustable, set by the ramp |
| VFD | about 1 to 1.5 | Lowest dip, but adds harmonics |
Example: a 250 kW motor, 0.9 power factor, 0.94 efficiency.
| Item | Value |
|---|---|
| Rated kVA | 250 ÷ (0.9 × 0.94) ≈ 295 kVA |
| DOL starting kVA (× 6) | ≈ 1,773 kVA |
Step 2Estimate the Voltage Dip
To a first approximation:
Dip (%) ≈ starting kVA ÷ short-circuit kVA at the bus × 100
The short-circuit capacity of the transformer alone is its kVA divided by its impedance. A 1,000 kVA unit with 6% impedance gives 16.7 MVA.
| Starting method (250 kW motor, 1,000 kVA, 6%) | Starting kVA | Dip |
|---|---|---|
| DOL | 1,773 | ≈ 10.6% |
| Star-delta | 591 | ≈ 3.5% |
| Soft starter (× 3) | 887 | ≈ 5.3% |
| VFD (× 1.2) | 355 | ≈ 2.1% |
These values use the transformer alone and ignore two effects that make the real dip larger. First, the upstream supply impedance sits in series with the transformer, so the short-circuit capacity at the bus is lower than 16.7 MVA. Second, the load already running on the transformer draws current before the motor starts, and its voltage drop adds to the starting surge — a bus that is already at about 90% loading, as in the worked example below, can see a dip noticeably higher than the table values. The estimate is for planning only, and a detailed study is needed for critical plants.
Step 3Check the Torque and the Limits
Voltage dip reduces motor torque with the square of voltage:
| Dip | Voltage at motor | Torque available |
|---|---|---|
| 10.6% | 89.4% | ≈ 80% |
| 8.5% | 91.5% | ≈ 84% |
| 5.3% | 94.7% | ≈ 90% |
Heavy-inertia loads such as crushers, compressors and fans may not accelerate if torque is too low. Allowed dip limits come from the project, the utility and the tool maker. Many specifications use about 10 to 15% at the motor terminals and lower values for sensitive loads.
Worked Example: Fixing a Failing Selection
Situation: a plant has a calculated running load of about 900 kVA — after the demand factor and without the motor-starting surge — and the largest motor is the 250 kW unit above. A standard 1,000 kVA transformer therefore leaves only about a 10% running margin, and the starting check below shows why that margin is not enough on its own.
| Option | Dip | Verdict |
|---|---|---|
| 1,000 kVA, 6%, DOL start | ≈ 10.6% | Borderline, torque only 80% |
| 1,250 kVA, 6%, DOL start | ≈ 8.5% | Acceptable, but larger and costlier |
| 1,000 kVA, 6%, soft starter | ≈ 5.3% | Acceptable, no transformer upsizing |
| 1,000 kVA, 6%, VFD | ≈ 2.1% | Best dip, check harmonics |
Often the cheapest fix is not a bigger transformer but a softer starter. If DOL is required, a larger or lower-impedance transformer works, but lower impedance raises the fault current and the mechanical stress on the windings during through-faults, so check breaker ratings and short-circuit withstand.
Step 4Consider Several Motors and Sequence
- Start motors one at a time. Simultaneous starts add their starting kVA.
- Check the already-running load. The dip from a new start adds to the drop caused by the load that is already on the transformer.
- Account for starts per hour. Frequent starts heat the windings.
- Review power factor. Low-power-factor motors raise the kVA the transformer must carry. Correct it carefully to avoid resonance.
Step 5Do Not Forget Harmonics and Inrush
- VFDs add harmonics. Ask for the spectrum and consider derating or a K-rated design. See dry-type transformer overheating.
- Energizing the transformer itself causes inrush, separate from motor starting: transformer inrush current.
- Voltage regulation. If the supply voltage varies, compare on-load vs off-circuit tap changers.
What to Put in the RFQ
- Largest motor rating and the starting method.
- Number of motors, starting sequence and starts per hour.
- Acceptable voltage dip at the transformer and at the motor.
- Upstream short-circuit level (MVA or kA).
- Impedance preference or tolerance range.
- Harmonic data for drives.
- Ambient conditions and any derating needs.
Our nameplate guide explains where kVA and impedance are marked, and our step-by-step selection guide covers the other parameters.
Matching Products to Motor Loads
Voltage and ratings follow your network and the plant design.
| Need | Aisite option |
|---|---|
| Distribution units, oil-immersed or dry-type | 10KV Transformer and 20KV Transformer |
| Higher-voltage intake for large plants | 35KV and above series |
| Packaged substation with motor feeders | Compact substation and HV LV Switchgear |
| A specific impedance or overload margin | Customized Transformer |
For plants in harsh conditions, see transformers for steel mill extreme environments and dry-type mining transformers.
Pre-Order Checklist
- Running load calculated with a demand factor
- Largest motor and starting method identified
- Voltage dip estimated and compared with the limit
- Torque at the dip checked for heavy-inertia loads
- Start sequence and starts per hour defined
- Upstream short-circuit level obtained
- Impedance chosen with the protection engineer
- Harmonic data requested for drives
FAQ
How much voltage dip is acceptable when starting a motor?
Many specifications use about 10 to 15% at the motor terminals, with lower limits for sensitive equipment. The exact limit comes from your project and utility.
Does a bigger transformer always fix the dip?
It helps, because the short-circuit capacity rises, but a softer starter or a VFD is often cheaper.
Why is torque reduced during a dip?
Because motor torque falls with the square of the terminal voltage.
Does lower impedance help?
It reduces the dip, but it also raises fault current, so breaker ratings must be checked.
Can Aisite quote to a specific impedance or starting requirement?
Yes. Send your motor list, starting method and limits, and our engineers will review them through the Customized Transformer line.
Standards and References
The estimates in this guide are planning-level. Detailed motor-starting and short-circuit studies should follow the applicable standards and the utility's rules. The most relevant references are:
- IEC 60076-1 — Power transformers — General (rating, impedance, temperature rise).
- IEC 60947-4-1 — Low-voltage switchgear and controlgear — Contactors and motor-starters (DOL, star-delta and soft-starter characteristics).
- IEC 60034-1 — Rotating electrical machines — Rating and performance (motor torque, current and starting classes).
- IEC 60909 — Short-circuit currents in three-phase a.c. systems (bus short-circuit capacity and fault levels).
- IEEE 399 — Recommended Practice for Industrial and Commercial Power Systems Analysis (motor-starting voltage-dip studies).
- IEEE 1346 — Recommended Practice for Evaluating Electric Power System Compatibility with Electronic Process Equipment (dip tolerance of sensitive loads).
- NEMA MG 1 — Motors and Generators (design letters and locked-rotor characteristics).
Confirm the editions and the project-specific limits with the responsible electrical engineer before finalizing a selection.
Get a Project-Specific Recommendation
Send your voltage, running load, largest motor, starting method and upstream fault level, and our engineers will suggest a configuration. Browse the full product range, view project cases, check the FAQ, or contact us.
This guide is general engineering information, not a substitute for a motor-starting study by a licensed engineer.

8615896663407