How to install Oil-Immersed Transformers properly?


Oil-immersed transformers are the backbone of power systems. Incorrect installation can lead to:

30%+ reduction in operational lifespan

Increased risk of oil leaks, fires, or explosions

Costly downtime and maintenance
Follow this IEC/IEEE-compliant guide to achieve optimal performance and safety.


Phase 1: Pre-Installation Preparation

✅ Critical Site Requirements

Foundation: 150mm reinforced concrete base with 1.5x transformer footprint

Clearances: ≥1.5m ventilation space around all sides (per NFPA 70)

Environmental Control: Humidity <85%, ambient temperature -25°C to +40°C

⚠️ Tools & Safety Checklist

EquipmentSpecification
Lifting GearCapacity ≥ 1.25x transformer weight
Insulation Tester5kV Megohmmeter
Oil Filtration Unit3µm filtration accuracy
PPEArc-flash suits, insulated gloves

Phase 2: Rigging & Positioning

▶️ Lifting Protocol (Key to Avoid Structural Damage)

Attachment Points: Use ONLY manufacturer-provided lifting lugs

Angle Control: Maintain <30° cable angle during hoisting

Landing Procedure:

Place on anti-vibration pads (≥10mm thickness)

Verify levelness: ≤2mm/m tolerance using laser level


Phase 3: Electrical Connections - IEC 60076 Standards

Connection TypeTorque ValueProtection Method
HV BushingsPer nameplate ±10%Silicone grease coating
LV Terminals50-60 N·mWeatherproof boots
Grounding25mm² copper cableDouble-bolt compression lugs

Pro Tip: Apply contact resistance tester after termination (value ≤10µΩ)


Phase 4: Oil Management - ASTM D3481

🔬 Oil Processing Flow
New Oil Delivery → Filtration (72hrs @ 60°C) → Dielectric Test (>50kV/2.5mm gap) → Vacuum Filling (<0.5mbar residual pressure)

📊 Oil Parameters Table

ParameterAcceptable RangeTest Method
Breakdown Voltage≥60 kVIEC 60156
Water Content≤15 ppmASTM D1533
Acidity≤0.03 mg KOH/gIEC 62021

Phase 5: Commissioning Tests

Essential Verification Sequence:

Insulation Resistance: HV-LV/Ground >1000 MΩ @ 40°C (IEC 60270)

Turns Ratio Test: ±0.5% of rated value

Winding Resistance: ±2% phase balance

DGA Baseline: Capture initial dissolved gas values

Critical: First energization at ≤33% load for 24hr thermal monitoring


Phase 6: Operational Safety Systems

⚠️ Mandatory Functional Checks

Pressure Relief Valve: Trip test @ 0.85 bar(g)

Buchholz Relay: Simulate gas accumulation alarm

OTI/WTI: Calibrate top oil/winding temperature indicators

Sudden Pressure Relay: Verify 5ms response time


Long-Term Maintenance Routine

IntervalKey Actions
DailyVisual oil level check, load recording
QuarterlyIR thermography scan of connections
AnnuallyDGA + Furan testing (IEC 60599)
5 YearsFull oil reconditioning

Why Trust AISITE Transformers?

✓ 15 Years Production Experience - and our products have been exported to over 50 countries and regions
✓ Certified Safety
✓ Technical Support - Access our professionals via the following ways:

📧 Email: [sale@aisite-ast.com]
📞 Phone/Whatsapp: [+86 15896663407]
🌐 Website: [https://www.aisite-ast.com/]

keyword:

oil immersed transformer,oil filled transformer,installation of transformer,installation of oil immersed transformer

RELATED NEWS

Contact information

Factory Address:500 meters southeast of Yilong Bridge in Yichuan, Luoyang, China


Copyright © 2023 Luoyang AISITE Transformer Co., LTD   Powered by www.300.cn  This site has IPV6 support   SEO

Business license

Search Here

全部
  • 全部
  • 产品管理
  • 新闻资讯
  • 介绍内容
  • 企业网点
  • 常见问题
  • 企业视频
  • 企业图册