Quick answer: A microgrid transformer solution connects several sources (PV, battery storage, generators) and the site load on one medium-voltage bus. Each source needs its own step-up transformer, and the whole system must start, run and fault in island mode, where the grid is weak. Size each transformer on its source's kVA rating, plan soft energization to limit inrush, choose low no-load losses because many units sit energized at low load, and package the equipment as an integrated substation to cut site work.

Why Hybrid Microgrids Are Growing

Remote mines, islands and rural towns are replacing diesel with solar and batteries:

  • According to pv magazine (July 2026), the Menzies microgrid in Western Australia aims to supply about 80% of the town's power from renewables, with diesel as backup. The same report notes Horizon Power operates 38 microgrids, and that a system near Exmouth with 9.6 MW of solar and a 10 MW / 49.6 MWh battery is close to completion.
  • RenewEconomy reported in June 2026 that an off-grid gold mine ran 155 consecutive hours on 100% renewables with its engines off.
  • AGL Energy is delivering a 9.2 MWp solar-plus-storage microgrid for a farm in South Australia (July 2026).

Each of these projects depends on transformers that connect different sources reliably, often in places where a failure means days of downtime.

Reference Architecture: Where Each Transformer Goes

Node Typical voltage Transformer role
PV inverter blocks 0.6–0.8 kV AC Step up to the MV bus
Battery storage (PCS) 0.4–0.69 kV Step up, bidirectional flow
Generators 0.4 kV (or MV) Step up, or connect directly at MV
Site loads MV to 0.4 kV Distribution step-down
Grid tie (if any) MV or HV Interconnection transformer
Illustrative 6 MW remote-site microgrid. PV, battery storage and generators connect to a medium-voltage bus through step-up transformers. Load transformers, a grounding transformer and an optional utility tie connect to the same bus. A microgrid controller coordinates all sources. Microgrid Single-Line Diagram (illustrative, 6 MW site) Microgrid controller (EMS / protection) PV array 5 MWac (inverters) Battery (BESS) 4 MW / 8 MWh (PCS) Generators 3 × 2 MW (0.4 kV) Utility grid (optional tie) 2 × 2,500 kVA 0.69 / 11 kV 2 × 2,000 kVA 0.69 / 11 kV 3 × 2,500 kVA 0.4 / 11 kV Tie transformer (if grid-tied) MV bus (e.g., 11 kV) LV 0.4 kVLV 0.4 kVLV 0.4 kV Load transformers: 5 × 2,000 kVA, 11 / 0.4 kV (N+1) Showing 3 of 5. Peak load 6 MW (≈ 6.3 MVA). About 63% loaded; 79% with one unit out. Grounding transformer (zigzag, neutral reference for island mode) 1 2 3 4 Black-start sequence (1) Grid-forming battery builds the bus with a voltage ramp. (2) Energize the PV step-up transformers one at a time. (3) Pick up loads in stages. (4) Start generators last, or on demand. Dashed lines = optional equipment or control signals. Ratings are illustrative and come from the 6 MW worked example. Not for construction.
Figure 1. Illustrative single-line diagram of a 6 MW remote-site microgrid. Numbers 1 to 4 show the black-start order.

For the storage and PV side, see why two-winding and double-split transformers suit storage and PV and our energy storage transformer guide.

Worked Example: 6 MW Remote Site

Assumptions (illustrative): 5 MWac PV, 4 MW / 8 MWh battery, 3 × 2 MW generators, 6 MW peak load at 0.95 power factor.

Item Transformer configuration
PV (5 MWac) 2 × 2,500 kVA step-up
Battery (4 MW) 2 × 2,000 kVA step-up
Generators (3 × 2 MW) 3 × 2,500 kVA step-up
Load (6 MW ≈ 6.3 MVA) 5 × 2,000 kVA distribution (N+1)
Load per unit, all five in service ≈ 63%
Load per unit, one out ≈ 79%

These numbers are for planning only. Final ratings come from the inverter, generator and load data, and the system study.

Step 1: Plan Black Start and Soft Energization

In island mode, nothing else holds the voltage while a transformer is switched on. Full-voltage energization causes inrush current that can collapse a weak bus. A common sequence:

  1. Grid-forming battery builds the bus with a voltage ramp.
  2. Energize transformers one at a time, starting with the PV step-up units.
  3. Pick up loads in stages.
  4. Start generators last, or on demand.

Ramping the voltage instead of switching it on at full value reduces inrush sharply. For the physics and settings, see our transformer inrush current guide.

Black-Start and Soft Energization Sequence (6 MW Microgrid Example) Illustrative timing and control logic for island-mode restoration ① BESS Builds Bus ② PV Transformers Energized ③ Loads Picked Up ④ Generators Started Grid-forming BESS Voltage ramp 2 × 2,500 kVA Closed One by One Limits inrush current Load Picked Up in Stages Avoids voltage dip Generators Started Last Or on demand Bus Voltage Active Power Voltage Ramp Soft Energization Load Step Synchronization Time t₀–t₁ t₁–t₂ t₂–t₃ t₃–t₄ Bus Voltage Active Power Note: Curves are illustrative. Actual timing depends on system study and controller settings.
Figure 2. Black-start sequence for a 6 MW microgrid: the grid-forming battery ramps the MV bus, PV transformers energize one by one, loads are picked up in stages, and generators start last.
Transformer Inrush Current vs. Soft Energization Comparison of bus voltage and current under island-mode energization A. Full-Voltage Energization (Without Soft Start) Current / Voltage High Inrush Peak Bus Voltage Dip Breaker Close Slow Decay B. Soft Energization (Voltage Ramp) Current / Voltage Low, Controlled Inrush Stable Bus Voltage Voltage Ramp Starts Inrush Current (Full Voltage) Inrush Current (Soft Energization) Bus Voltage
Figure 3. Full-voltage energization produces a high inrush peak and a bus voltage dip; soft energization with a voltage ramp keeps both under control.

Step 2: Check Fault Level and Protection

Inverters limit fault current, typically to about 1.1–1.5 times rated current. In an island with few generators, the fault current may be too low for conventional overcurrent protection to trip quickly.

  • Run a short-circuit and coordination study for island and grid-connected modes.
  • Keep a generator online where protection needs more fault current, or use schemes designed for inverter-based systems.
  • Review transformer impedance with the protection engineer. A lower value raises fault current but also affects voltage regulation. If the bus voltage must be held tightly, compare on-load vs off-circuit tap changers.

Step 3: Grounding the Island

An islanded MV system needs a defined neutral reference. Options include a grounded-wye winding or a zigzag grounding transformer. Read our grounding transformer guide for how they work.

Step 4: Count No-Load Losses

PV and battery transformers stay energized all year, including at night and at partial charge. Their average load factor is low, so no-load losses dominate.

Example: a transformer with 2.5 kW of no-load loss uses 2.5 × 8,760 ≈ 21,900 kWh per year. If that energy came from a diesel generator at about 0.27 L/kWh, it equals roughly 5,900 liters of fuel. Each kilowatt of no-load loss costs about 2,400 liters per year in this logic. Evaluate losses over the life of the project, as explained in our transformer lifespan guide.

No-Load Loss Annual Cost: 2.5 kW Transformer How a small no-load loss translates into significant diesel fuel consumption Transformer No-Load Loss 2.5 kW Annual Energy 2.5 kW × 8,760 h 21,900 kWh Diesel Equivalent 21,900 kWh × 0.27 L/kWh ≈ 5,900 L/year Cost per kW Every 1 kW no-load loss ≈ 2,400 L/year Key takeaway: In remote microgrids, PV and battery transformers stay energized all year at low average load. Choosing low no-load loss designs directly reduces diesel fuel consumption and operating costs.
Figure 4. Annual no-load loss cost of a 2.5 kW transformer: about 21,900 kWh per year, roughly 5,900 liters of diesel, or about 2,400 liters per year for every 1 kW of no-load loss.

Step 5: Package as an Integrated Substation

Remote sites have limited cranes, roads and skilled labor. Factory-built skids cut risk:

  • PV block skid: transformer, MV switch and LV board on one base.
  • Battery block skid: transformer matched to the PCS.
  • MV switchgear and load centers in a prefabricated enclosure.

See our E-House prefabricated modular substation guide, the prefab substation buying guide, and temperature control for prefabricated substations. Check transport weight and dimensions against the haul route early.

Step 6: Standards and Interconnection

Interconnection rules and controller requirements vary by country. Commonly referenced documents include IEC 60076 for transformers, IEEE 1547 for interconnection, and IEEE 2030.7 for microgrid controllers. Confirm the edition and local requirements with your engineer and utility.

Matching Products to the Microgrid

Microgrid node Aisite option
PV and storage step-up New Energy Transformer
MV distribution and loads 10KV Transformer and 20KV Transformer
Larger sites, higher collection voltage 35KV and above series
Packaged power block Compact substation
MV and LV switching HV LV Switchgear
Special voltage, impedance, grounding or sound limit Customized Transformer

If your project is a grid-tied PV plant without generators or an island mode, our Solar PV Electrical Infrastructure: Integrated Solution Guide is the better starting point. For system-level references, see our Energy Storage and Photovoltaic power generation solution pages. For choosing and buying, use our power transformer selection guide.

Pre-Order Checklist

  • Source ratings (PV, battery, generator) and peak load documented
  • Island and grid-connected modes defined
  • Black start and energization sequence agreed with the controller supplier
  • Short-circuit and protection study completed
  • Grounding method chosen
  • No-load and load losses evaluated over project life
  • Environmental conditions and haul route confirmed
  • Spare capacity and expansion plan defined

FAQ

Do microgrids need special transformers?

Often standard designs work, but ratings, impedance, grounding and losses must be matched to inverter, generator and island-mode behavior.

What is black start in a microgrid?

Restoring power from zero without the main grid. Typically a grid-forming battery builds the bus voltage, then transformers and loads are energized in steps.

Why do no-load losses matter more in a microgrid?

Many transformers stay energized all year at low average load, so no-load losses are most of their total.

Can Aisite build to a site-specific voltage or grounding requirement?

Yes, through the Customized Transformer line, based on project requirements.

Get a Project-Specific Recommendation

Send your PV, battery and generator ratings, peak load, voltages, site conditions and haul route, and our engineers will suggest a configuration. Browse the full product range, check the FAQ, or contact us.

This guide is general engineering information and not a substitute for a system study by a licensed engineer.